Our friends as Bragg involved Atlas Rigging & Transfer in a specialty rigging project moving heavy air handler units. Atlas was hired to rig in air handler units, two scissor lifts, and pipe racks set on the fifth floor. Each of the air handler units weighed over 4500 pounds.
Atlas fabricates rigging platforms to help move heavy machinery and other equipment into a building where there is limited access to safely do it. Atlas designs a platform to hold in excess of the weight needed and includes strategic connection points, rails, and a ramp for efficient and safe rigging.
The platform used in this job can help install up to 30,000 pounds of equipment, up to a 20-story tall building, with a side opening in the building.
Check out some of the photos and a video (video speed increased for quicker viewing) from the job site.